Type : Bid Notification
Cyclone Sports Complex-Soccer Field-Replacement Prebid Meeting: 11/30/2022 1:00:00 PM Prebid location: via WebEx Tour: 11/30/2022 Following Prebid Meeting Bid date: 12/15/2022 Bid opening online Substantial completion: July 14, 2023 Cost estimate: $660,000 TSB goal: 10% Project manager: Angela Solberg asolberg@iastate.edu 515-509-3086 Construction manager: Nathan Graves