  • Mallard Creek WRF Improvements Phase I (Bid Packages 15.25 and 15.30)

    Type : Bid Notification

    Due : 15 Dec, 2022 (15 months ago)
    Posted : 15 months ago
    Started : 23 Nov, 2022 (16 months ago)

    PC/Leeper Joint Venture has been selected by Charlotte Water as the construction manager for the Mallard Creek Water Reclamation Facility Phase 1 Improvements project in Charlotte, North Carolina. This project includes process air and liquid and solids process train improvements that will allow the facility to expand from its current 12-mgd capacity to 14.9 mgd.

    From: Charlotte (City)

  • Mallard Creek WRF Improvements Phase I (Bid Packages 13.01, 15.25, 15.30)

    Type : Bid Notification

    Due : 07 Dec, 2022 (15 months ago)
    Posted : 17 months ago
    Started : 22 Nov, 2022 (16 months ago)

    PC/Leeper Joint Venture has been selected by Charlotte Water as the construction manager for the Mallard Creek Water Reclamation Facility Phase 1 Improvements project in Charlotte, North Carolina. This project includes process air and liquid and solids process train improvements that will allow the facility to expand from its current 12-mgd capacity to 14.9 mgd.

    From: Charlotte (City)

  • Mallard Creek WRF Improvements Phase I (Bid Packages 2.01, 2.02, and 2.03)

    Type : Bid Notification

    Due : 09 May, 2022 (22 months ago)
    Posted : about 2 years ago
    Started : 18 Mar, 2022 (about 2 years ago)

    Headworks, EQ storage, chemical improvements, new screenings facilities, new influent pump station, solids handling improvements and odor control. PC/Leeper joint venture has been selected by Charlotte Water as the construction manager for the Mallard Creek Water Reclamation Facility Phase 1 Improvements project in Charlotte, North Carolina.

    From: Charlotte (City)

  • Mallard Creek WRF Phase 1 Improvements Construction Manager at Risk Services

    Type : Bid Notification

    Due : 04 Mar, 2021 (about 3 years ago)
    Posted : about 3 years ago
    Started : 17 Feb, 2021 (about 3 years ago)

    The Mallard Creek Interceptor improvement project is a multi-phased sewer improvement project that will extend from the Mallard WRF influent pumping station, to Toby Creek, near North Tryon Street, in its first phase. With program management oversight from Brown and Caldwell, the CMAR will coordinate work with the DB team for the interceptor design and construction within the plant site.

    From: Charlotte (City)

  • Mallard Creek WRF Phase 1 Improvements - Prequalification for Early Work Package 1

    Type : Bid Notification

    Due : 16 Mar, 2022 (about 2 years ago)
    Posted : about 2 years ago
    Started : 31 Jan, 2022 (about 2 years ago)

    Description: PC / Leeper Joint Venture is accepting applications for subcontractor prequalification for the Mallard Creek WRF Phase 1 Improvements Early Work Package 1.

    From: Charlotte (City)

  • Mallard Creek WRF Phase 1 Improvements - Prequalification for Work Package 3

    Type : Bid Notification

    Due : 17 Oct, 2022 (17 months ago)
    Posted : 18 months ago
    Started : 05 Sep, 2022 (19 months ago)

    Description: PC / Leeper Joint Venture is accepting applications for subcontractor prequalification for the Mallard Creek WRF Phase 1 Improvements Work Package 3. Package 13.01 – Equalization Facilities In general, the scope of work consists of the work required to construct two new Equalization Tanks for the MCWRF Phase 1 project.

    From: Charlotte (City)

  • Mallard Creek WRF Phase 1 Improvements - Prequalification for Early Work Package 2

    Type : Bid Notification

    Due : 01 Jul, 2022 (21 months ago)
    Posted : 22 months ago
    Started : 16 Jun, 2022 (21 months ago)

    Description: PC / Leeper Joint Venture is accepting applications for subcontractor prequalification for the Mallard Creek WRF Phase 1 Improvements Early Work Package 2. Electrical Description: In general the scope of work consists of the supply and installation of all electrical components for the new influent pump station for the MCWRF Phase 1 project.