Type : Bid Notification
The Project is located on Interstates 5, 8, and 15, and Routes 52, 67, 75, 79, 94, and 125, in the County of San Diego at various locations. The project aims to construct portions of the middle-mile broadband network within State Right of Way. A more detailed description of the Project is contained in Appendix A. The estimated cost of this CMGC Project (in 2022 US dollars) is $55.63 million for construction capital and $1.6 million for Right of Way capital (including utility relocation). 2 - Procurement Schedule Final Date for Receipt of Proposers¿ Questions-11/21/2022 SOQ Due Date for Electronic and Hardcopy Submittal-12/14/2022 Anticipated Ranking Determination-1/6/2023 4.2 Quantities, Due Date, Time, and Location: The original and an ele...