RFI Question and Answer: 14-Dec-22Will the new units require fire alarm integration (duct detector and shut down)? The existing Monaco system does not look like it can be expanded.Answer: Duct detectors are required according to the latest NEC standards. They should be included. The systems will not be integrated into the Monaco system.Ammendment to solicitation 14 Dec-22 - Updated SOW to clarify language in section 5 (in Attachments/Links). Provided answers to RFI (in Attachments/Links)Ammendment to solicitation 4-Dec-22 - Change the PoP from 270 to 180 days. Ammended 1442 is in attachments.See the attached 1442 Solicitation for the Replacement of Building 5 HVAC Units at the Combat Readiness Training Center, Gulfport, MS. Procurement and installation of two (2), 10 ton 208/230 volt 3 phase packaged units for building 5 Community Center.Information for the site visit scheduled 8 December 2022 @ 0900 CST is included in the Instructions to Offerors.The Construction Wage Rate Requirements, formerly known as Davis Bacon Wage Rates, are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are MS20220050 10/07/2022 MOD3 for Harrison County, Mississippi.