The project entails the installation of approximately 5,110 LF of 6-inch HDPE and 340 LF of 6-inch PVC Force Main along Mariposa Avenue starting at SE Lennard Road and ending west of SE Calais Street. The project will be constructed by horizontal directional drill except for the required connections at the ends of the project and connections of drill lengths, which will be installed by open cut. The eastern leg of the force main connects the 6-inch force main located at the Lift Station SP-50. To the western leg of the force main will connect to an active 16-inch force main of the intersection of Lennard Road and Mariposa Avenue. The project is to include all fittings, valves, appurtenances, and pipe associated with the installation of the horizontal directional drill in addition to all fittings, valves, appurtenances, and pipe associated with the open installation of the C-900 PVC force main, connections to the existing force mains, grouting and abandoning in place existing force
mains and obtaining of any required permits. All work shall be in accordance with the Technical Specifications and Constructions Plans prepared by CivilSurv Design Group, Inc. consisting of the pages (1-79)...(Attachment A & B) The Work consists of furnishing all labor, equipment, and materials for the construction of the facilities consisting of, but not limited to the following: • Horizontal Directional Drills (HDD) as defined in the plans. • Open cut installation and repairs to pavement and concrete as defined in the plans. • Wet taps as defined in the plans. • Grout filling and abandoning existing piping identified in the plans. • Maintenance of Traffic and Maintenance of Drainage, provided by Contractor. The Contractor shall provide all materials, supplies, labor and equipment necessary for a complete project based on all specifications and any contract amendments that may be deemed necessary. The construction contract period is one hundred eighty (180) calendar days with no option to renewal. The Contractor must have all the required licenses and certifications necessary to perform this work. The approved licenses for this project include a Underground Contractor License, and/or a State of Florida General Contractor License. It is the Contractor’s responsibility to verify with the City’s Building Department that they possess the proper licenses and certifications to perform the work prior to submitting a bid.Show Less