Start/Delivery Date
The project should start by July 1, 2022
Project Duration
90 days
Bid Bond
Bid Bond
0.00%
Payment Bond
0.00%
Performance Bond
0.00%
Pre-Bid Meeting Information
Pre-Bid Meeting
Yes - Mandatory
Pre-Bid Meeting Date
05/27/2022 10:00 AM (PDT)
Pre-Bid Meeting Location
1200 S. Carpenter Rd #35, Modesto CA 95351
Online Q&A
Online Q&A
No
Contact Information
Contact Info
Samuel Perez, Housing Rehab Specialist I
Housing@Modestogov.comBids to
Bids are to be submitted electronically to
Housing@Modestogov.comOwner's Agent
Description
Scope of Services
GFCI, Window Installation, HVAC, Smoke and Carbon Monoxide Detector Installation
Other Details
Work Write-Up available at Suite 3100 Customer Service Counter or Download.
Please submit a contractor application and upload all insurance requirements into PINSAdvantage.
Notes
This is a HUD funded project; Section 3 businesses and or/business that employ Section 3 residents are encouraged to respond
Special Notices
Local Programs & Policies
An engineer’s estimate is “NOT” released for this project. The project is “NOT” subject to prevailing wage.