Mel Price Lock & Dam Lift Gate Install & Machinery Replacement

expired opportunity(Expired)
From: Federal Government(Federal)
W912P923R0042

Basic Details

started - 01 May, 2023 (12 months ago)

Start Date

01 May, 2023 (12 months ago)
due - 15 May, 2023 (11 months ago)

Due Date

15 May, 2023 (11 months ago)
Pre-Bid Notification

Type

Pre-Bid Notification
W912P923R0042

Identifier

W912P923R0042
DEPT OF DEFENSE

Customer / Agency

DEPT OF DEFENSE (709057)DEPT OF THE ARMY (133116)USACE (38131)MVD (4899)W07V ENDIST ST LOUIS (868)
unlockUnlock the best of InstantMarkets.

Please Sign In to see more out of InstantMarkets such as history, intelligent business alerts and many more.

Don't have an account yet? Create a free account now.

PRE-SOLICITATION SYNOPSISMELVIN PRICE LOCK & DAM MAIN LOCK LIFT GATE INSTALL & MACHINERY REPLACEMENTCONTRACTING OFFICE ADDRESS: 1222 Spruce Street, St. Louis, MO 63104POINT OF CONTACT: Angie Grimes, Contract Specialist, angie.l.grimes@usace.army.milPROPOSED SOLICITATION NUMBER: W912P9-23-R-0042PLACE OF CONTRACT PERFORMANCE: Alton, IllinoisCOMPETITION SET-ASIDE: Full & Open CompetitionTYPE OF PROPOSED CONTRACT: firm fixed price (FFP), Request for Proposal (RFP)PERIOD OF PERFORMANCE: 20 months after date of awardESTIMATED MAGNITUDE: between $5,000,000 and $10,000,000PRODUCT OR SERVICE CODE (PSC): Y1PZ – Construction of Other Non-Building FacilitiesNAICS AND SIZE STANDARD: The North American Industry Classification System (NAICS) code for this is effort is 237990, Other Heavy and Civil Engineering Construction. The Small Business Administration small business size standard for NAICS code 237990 is $39.5 million annual
average receipts (total or gross income) over the past three years.DESCRIPTION:General Site Description:Melvin Price Locks and Dam is located on the Mississippi River near Alton, Illinois, approximately 21.3 river miles upstream from St. Louis and 200.8 miles above the mouth of the Ohio River. The project consists of a main lock and an auxiliary lock; a dam containing nine Tainter gates; and a fixed submersible dike reaching the Missouri Side of the River. The main lock is 1200 ft by 110 ft with a lift gate at the upstream end and a miter gate at the downstream end of the lock chamber. The auxiliary lock is 600 ft by 110 ft with a set of miter gates at the upstream and downstream ends.Work Statement:The work will consist of furnishing all labor, equipment, operators, supervision, supplies and materials, and incidentals necessary to perform the Melvin Price Locks and Dam Lift Gate Install and Machinery Replacement Project. The work is anticipated to be accomplished with traditional river marine construction equipment, such as floating plant and barge mounted crane, and staged behind the bulkheads on the upstream end of the main lock. All heavy lifts to include the removal of the existing lift gate leaves, installation of the new lift gate leaves, and removal/installation of the maintenance bulkheads will be performed by the Government. However, full coordination will be required between the Government and the Contractor during the removal and installation processes. The contractor will be required to install Government Furnished unwatering pumps and maintain the pumps during the duration of the unwatering. Once work has been accomplished coordination will be required to ensure that the lock is properly rewatered, bulkheads removed, and main lock put back into operation per the schedule. The work will be performed during a scheduled closure of the main lock which is currently estimated to occur in the winter timeframe starting between December 2024 and January 2025 and ending between March and April 2025. Main lock closure is expected to be a no more than 90-days, main lock will only be closed for a maximum of 90 consecutive days. The main lock work must be fully completed with commissioning and acceptance accomplished 7-days before lock opening date. The structural work on the project includes but is not limited to the following:Working with the Government to assist with the final installation of the replacement government furnished two leaf lift gate. The Contractor must be able to follow a detailed sequence given in the specifications for the work that will be coordinated with the Government for the installation of the replacement lift gate. Removal of existing counterweights.Fabrication and installation of the replacement counterweights.Installation of reinforced concrete lift gate sill raise and gate rests.The mechanical work on the project includes but is not limited to the following:Removal of select lift gate machinery components.Supply and installation the new vertical lift gate machinery components.Installation of the hoisting and counterweight wire ropes after the Government installs the replacement lift gate leaves.The electrical work includes but is not limited to the following:Replacement of low-voltage 480VAC motor control centers (MCC) including removal of existing MCCs, installation of new MCCs, and replacement of various power feeder cables.Replacement of low-voltage 480VAC electric hoist motors, adjustable speed drive (ASD) motor controller enclosures, and various power feeder cables and control devices.Programming, start-up, and testing of ASD motor controller systems and integration of new ASD systems with existing Lock PLC/HMI system.Modifications to existing Lock PLC/HMI system program to accommodate specific operating parameters of the new lift gate.Once the machinery is properly aligned and the PLC/HMI system modifications are complete, commissioning will be required to calibrate and hone gate travel limits and operational speeds prior to acceptance.SOLICITATION: The solicitation is expected to be available on or about May 15, 2023. The proposal submission date and time will be contained in the solicitation package. For changes to the issue date or any other changes to the information in this synopsis, potential offerors are responsible to check the information on the System for Award Management at www.sam.gov/. This solicitation package will be posted on SAM, which can be accessed at www.sam.gov/. Paper copies of this solicitation and its amendments will not be available or issued. Telephone, written, facsimile, or e-mail requests for the solicitation package or the Interested Vendor List will not be honored. This notice does not obligate the Government to award a contract, nor does it obligate the Government to pay for proposal preparation costs. SYSTEM FOR AWARD MANAGEMENT (SAM.gov): Be advised that all interested parties MUST be registered in the System for Award Management (SAM) Database at https://www.sam.gov, in order to receive notification and/or changes to the solicitation, and to receive a contract award. The Interested Vendor List will be activated and may be accessed and printed from this web site. Prospective offerors who would like their company name included on the Bidders Mailing List (plan holders list) may do so on the SAM website under Interested Vendor List. Potential offerors are responsible for monitoring this site for the release of the solicitation package and any other pertinent information and for downloading their own copy of the solicitation package.

Location

Place Of Performance : N/A

Country : United StatesState : IllinoisCity : Alton

Classification

naicsCode 237990Other Heavy and Civil Engineering Construction
pscCode Y1PZCONSTRUCTION OF OTHER NON-BUILDING FACILITIES