Maintenance Dredging of Fire Island Inlet and Shores Westerly to Jones Inlet Beach Erosion Control and Navigation Project

From: Federal Government(Federal)
W912DS24B0003

Basic Details

started - 26 Apr, 2024 (2 days ago)

Start Date

26 Apr, 2024 (2 days ago)
due - 09 May, 2024 (in 10 days)

Due Date

09 May, 2024 (in 10 days)
Bid Notification

Type

Bid Notification
W912DS24B0003

Identifier

W912DS24B0003
DEPT OF DEFENSE

Customer / Agency

DEPT OF DEFENSE (709024)DEPT OF THE ARMY (133114)USACE (38130)NAD (5840)W2SD ENDIST NEW YORK (593)

Attachments (41)

unlockUnlock the best of InstantMarkets.

Please Sign In to see more out of InstantMarkets such as history, intelligent business alerts and many more.

Don't have an account yet? Create a free account now.

The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging and beach nourishment of Fire Island Inlet and Shores Westerly to Jones Inlet Beach Erosion Control and Navigation Project, New York. The work consists of dredging the Fire Island Inlet Federal Navigation channel and deposition basin with subsequent placement of the dredged sand as nourishment along the designated feeder beach (Gilgo Beach, Suffolk County, New York).The proposed dredging and beach nourishment work would involve dredging and placement of approximately 700,000 to 1,000,000 CY of sand at Gilgo Beach, subject to available funding. The project is scheduled to be dredged to a depth of 14 feet plus 2 feet allowable over-depth.The purpose of the proposed work is to alleviate the effects of shoaling and maintain the project dimensions, thereby providing safe and economical use of the Fire Island Inlet waterway by commercial and recreational boating interests while
providing beneficial use of the dredged sand. Between maintenance operations, the bypassed sand placed at the feeder beach would be carried by littoral drift to feed down drift beaches. The maintenance operation would thus serve to place sand trapped in the channel back into the normal littoral movement that naturally replenishes the western beaches, while maintaining a safe channel for navigation.The proposed work can be accomplished by large pipeline dredge and must meet US Coast Guard criteria for an “ocean going vessel”.The Contractor will be required to commence work within five (5) calendar days after the date of receipt by him of the notice to proceed, and to prosecute said work diligently and to complete the basic work ready for use not later than ninety-seven (97) calendar days after the receipt by him of the notice to proceed (NTP). The contractor is required tomaintain an integrated production of at least 13,500 cubic yards per calendar day.The work is estimated to cost between $15,000,000 and $50,000,000. Plans and specifications for the subject project would be available in March 2024, with bid opening in April 2024. It is the intention of the government to award in May and NTP in first week of October 2024.Liquidated Damages of $2,390.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete.This is an unrestricted Procurement.

NY   USALocation

Place Of Performance : N/A

Country : United StatesState : New York

Office Address : KO CONTRACTING DIVISION 26 FEDERAL PLAZA ROOM 16 300 NEW YORK , NY 10278-0004 USA

Country : United StatesState : New YorkCity : New York

Classification

naicsCode 237990Other Heavy and Civil Engineering Construction
pscCode Y1KFCONSTRUCTION OF DREDGING FACILITIES