Public Works Bid | S10 Generator, Well Pump, and Site Improvements Deadline:April 02, 2024 Department:Public Works Release Date:February 26, 2024 Plans - Publication Date: February 26, 2024 Specifications - Publication Date: February 26, 2024 Bid Opening Live Stream - Publication Date: February 26, 2024 Addendum 1 - Publication Date: March 12, 2024 Addendum 2 - Publication Date: March 20, 2024 This contract provides for the installation of approximately 70 linear feet (LF) of 12-inch diameter water main, approximately 80 LF of 12-inch diameter PVC storm piping, replacement of an existing vertical turbine well pump with a submersible pump, rehabilitation of an existing well, installation of a below grade vault, replacement of an existing sodium hypochlorite metering and monitoring system, and installation of a new, diesel-powered generator with sub-base fuel tank. The project also includes electrical, site, and restoration activities associated with the project components listed