The NORTH CREEK TRAIL SECTION 4 - PHASE 2 AND PHASE 3 proposes to construct a shared usenon-motorized path between the Centennial Park driveway and the North Creek Trail Section 3terminus along the south side of SR524. The general aspects of this work will involve construction ofapproximately 1,875 linear feet of 10-foot-wide paved trail with planter strip, mechanically stabilized earthwall, soldier pile wall, a moment slab over the existing Filbert Creek box culvert, pedestrian bridge crossingof North Creek, construction of approximately 1,758 linear feet of 12-inch-diameter water main, street lightrelocation, erosion control, site preparation, fencing, and utility adjustments. The total estimated cost forthis project is in the range of $4,360,000 to $4,820,000. The number of working days for PhysicalCompletion of this project is 190. Please contact Yongqing Zhu, P.E., at (425) 806-6830 for any questionsregarding this