RI-138A, Aquidneck Ave (East Main Rd to Green End Ave)

expired opportunity(Expired)
From: Rhode Island(State)
TCB22000807

Basic Details

started - 16 Dec, 2021 (about 2 years ago)

Start Date

16 Dec, 2021 (about 2 years ago)
due - 21 Jan, 2022 (about 2 years ago)

Due Date

21 Jan, 2022 (about 2 years ago)
Bid Notification

Type

Bid Notification
TCB22000807

Identifier

TCB22000807
State of Rhode Island

Customer / Agency

State of Rhode Island

Attachments (22)

unlockUnlock the best of InstantMarkets.

Please Sign In to see more out of InstantMarkets such as history, intelligent business alerts and many more.

Don't have an account yet? Create a free account now.

info Contact Information Solicitation Number :
TCB22000807 from
Dept of Transportation Lisa Hill
One Capitol Hill 2nd Floor Providence RI, 02908 United States
Tel: (401) 574-8118
Fax:
lisa.hill@purchasing.ri.gov library_books Solicitation Categories No Categories available shopping_cart Solicitation Items No. Spec. Number Name Manufacturer Name Qty Unit Delivery Address Desired Delivery Date 1 201.0301 CUTTING AND DISPOSING ISOLATED TREES AND STUMPS (4"- 24") 4 each 2 201.0306 COMPLETE REMOVAL AND DISPOSAL OF ISOLATED STUMPS (24'' OR PLUS) 1 each 3 201.0310 REMOVE AND DISPOSE SHRUBS 20 each 4 201.0402 REMOVE AND DISPOSE CONCRETE CURB 1675 linear foot 5 201.0403 REMOVE AND DISPOSE SIDEWALKS 120 square yard 6 201.0409 REMOVE AND DISPOSE FLEXIBLE PAVEMENT 6500 square yard 7 201.0410 REMOVE AND DISPOSE CATCH BASINS 3 each 8 201.0414 REMOVE AND DISPOSE PIPE - ALL SIZES 1400 linear foot 9 201.0415
REMOVE AND DISPOSE GUARDRAIL AND POST ALL TYPES 90 linear foot 10 201.0418 REMOVE AND DISPOSE HYDRANT 1 each 189 total 1 2 3 4 5 attachment Solicitation Attachments Mandatory Documents 1. DOT US OMB Lobbying Form.pdf 2. DOT USDOT Standard Title VI Assurances for Contractors.pdf 3. 2019-CH-092 Plans.pdf 4. 2019-CH-092 Contract Book.pdf 5. Federal Wage Rate.pdf 6. DBE Affirmative Action Cert. 08-24-20.pdf 7. DOT Anti-Collusion.pdf 8. DOT Certification Regarding Debarment.pdf 9. DOT Conflicts Disclosure Policy.pdf 10. DOT Requirement for Affirmative Action To Ensure EEO.pdf 11. 2019-CH-092 Distribution of Quantities.pdf Addendum Documents 1. RIC 2019-CH-092 ADDENDUM 2 COVER LETTER.pdf 2. 2019-CH-092 Contract Book_AddendumNo2.pdf 3. 2019-CH-092 Plans_AddendumNo2.pdf 4. Federal Wage Rates_AddendumNo2.pdf 5. 2019-CH-092 Distribution of Quantities_AddendumNo2.pdf 6. RIC 2019-CH-092 ADDENDUM 1 COVER LETTER.pdf Solicitation Addenda 1. VendorChangeDetailsReport_TCB22000807_v2_Jan_14_22.pdf chat Solicitation Questions & Answers Question Answer Item 701.8002 Pipe B bedding is bedding for under the drainage and water pipe. If water is encountered in the excavation, how will class c bedding be paid for?
January 12, 2022 at 3:00:44 PM GMT Dewatering is the responsibility of the Contractor and is incidental to the work. Class C Bedding if used, will be at the Contractor’s convenience and it will not be reimbursed. If encountered and at the approval of the Engineer, unsuitable material will be replaced with Class B bedding in 8” lifts in accordance with the Specifications.
January 13, 2022 at 5:38:52 PM GMT Bid item # 47 -24" Ductile iron sewer safe class 52 pipe is called out on the plans as RCP (sheet #47 STA 34+02) but is Called out as Ductile iron sewer safe class 52 in the DOQ please clarify what pipe should be installed at this location.
January 07, 2022 at 4:58:25 PM GMT 24" Ductile Iron Sewer Safe Class 52 pipe shall be installed at this location. Plans will be revised accordingly in Addendum No. 2
January 13, 2022 at 1:42:31 PM GMT Are paving and Reclamation the only operations allowed at night, during those TMP hours? (11pm - 6am)
January 07, 2022 at 4:06:12 PM GMT Other activity, when approved by the Engineer, may be performed at night but only between Vierra Terrace and Green End Avenue. Only paving and reclamation activities are permitted at night between Vierra Terrace and East Main Road, unless directed by the Engineer. The Contract Book will be updated by addendum.
January 13, 2022 at 8:59:49 PM GMT How is Trimming and Finegrade Paid for in the Reclaimed areas. The Item states it should be inclusive of the Reclaim item, but the DOQ shows that area being Finegraded. Please Clarify.
January 07, 2022 at 3:55:04 PM GMT Cost of Trimming and Fine Grading for the reclaimed areas is included in the cost of item 406.9901 Full Depth Reclamation with Calcium Chloride. Quantity of item 204.0100 Trimming and Fine Grading will be revised in Addendum No. 2.
January 13, 2022 at 1:45:36 PM GMT Temporary 3" patching for water installations calls out for class 12.5 HMA. Temporary patching for drainage installations calls for 2" class 9.5 HMA. The distribution of quantities shows a quantity of 150 tons for drainage work contingency, however there is no quantity shown for trench patching for water installation. Also, there is not a bid item for class 12.5 HMA for water trench patching. Why is there different HMA type requirements for the different utility trench patching? A temporary trench patch is a temporary trench patch and should require the same HMA type?
January 06, 2022 at 4:30:05 PM GMT Patching for both water and drainage installation shall be 2" class 9.5 HMA. Plans and DOQ will be revised accordingly in Addendum No. 2.
January 13, 2022 at 1:46:57 PM GMT Will you accept the required Bid Bond to be submitted as an attachment? I don't see instructions for an acceptable way to submit it.
January 05, 2022 at 4:54:36 PM GMT Correct, Contractors are to upload the required Bid Bond as an attachment to their bid offer.
January 12, 2022 at 6:13:58 PM GMT Item number 127 is duplicated. IE: Item # 127 temporary Construction Signs STD 29.1.0 and 27.1.1, Item Number 127 Drum Barricade STD 26.3.0. will these item numbers be changed to proper order?
January 05, 2022 at 1:51:37 PM GMT Item numbers will be revised via Addendum No. 2.
January 13, 2022 at 1:47:52 PM GMT Sheet #7/note #4 states that reclaimed gravel material can be used in lieu of gravel borrow subbase course. If this occurs does the contractor get paid for the initial earth excavation, as described in the full depth reclamation notes, and also for the gravel borrow subbase?
January 04, 2022 at 3:49:07 PM GMT The Contractor shall be paid for removal of excess reclaimed material under item 202.0100 Earth Excavation. The intent is to reuse the reclaimed material whenever possible. When unsuitable materials are encountered and when approved by the Engineer, the Contractor will be compensated for using the reclaimed gravel material as a substitute for Gravel Borrow Subbase under item 302.0100 Gravel Borrow Subbase Course.
January 13, 2022 at 1:48:41 PM GMT How will measurement for excavation of recycled roadway excess material be measured for payment? How will the total of material be determined in the field?
January 04, 2022 at 3:39:13 PM GMT Measurement of excess material will be as described in Section 109.01 of the Standard Specifications.
January 13, 2022 at 1:49:13 PM GMT Will there be a pre bid meeting for this proposal?
December 22, 2021 at 4:44:35 PM GMT There will not be a pre-bid meeting for this proposal.
December 23, 2021 at 2:09:31 PM GMT 11 total 1 2

Lisa Hill One Capitol Hill 2nd Floor Providence RI, 02908 United StatesLocation

Address: Lisa Hill One Capitol Hill 2nd Floor Providence RI, 02908 United States

Country : United StatesState : Rhode Island

You may also like

Florida Ave Culvert Project

Due: 16 Apr, 2024 (in 17 days)Agency: Amsterdam, City of

No. 2 Rd Multi-Use Pathway from Steveston Hwy to Williams Rd

Due: 18 Apr, 2024 (in 19 days)Agency: City of Richmond

CDBG South Ridgewood Ave East Side Sidewalk Improvements