From: Federal Government(Federal)
Basic Details | Start Date25 Sep, 2021 (about 2 years ago)Due Date29 Sep, 2021 (about 2 years ago) |
Customer / Agency | |
Supplier | |
Work associated w ith this requirement includes the rehabilitation of both the upper and low er miter gates at the NASA SSC Canal Navigation Lock. A miter gate consists of a left and right-hand leaf that are opposite hand but otherw ise identical. The Contractor shall remove and lay flat each miter gate leaf on a deck barge for rehabilitation. Government-furnished lock chamber stop-logs may need to be installed at the upper end of the lock, depending on the Contractor’s w ork plan. The miter gate rehabilitation consists of blasting and painting the gates, replacement of all timber fenders, replacement of miter gate rubber seals, and structural member replacement and repair. Rehabilitation also includes cathodic protection system removal, repair, installation, and testing by corrosion expert in accordance with