Type : Bid Notification
PROJECT SCHEDULE TASK BEGIN COMPLETE Construction Document Phase 03/07/2024 08/14/2024 Bid/Negotiation Phase 09/24/2024 11/05/2024 Construction Phase (There is an early abatement & demo package scheduled to start 6/26/2024) 12/9/2024 ♦ O&M Manuals ♦ 04/18/2026 Training ♦ 04/28/2026 Substantial Completion ♦ 5/06/2026 Final Completion ♦ 05/25/2026 NOTE: The schedule indicated above is contingent upon several enabling packages, obtaining funding, and